A new real estate project relies on a precise legal mechanism: the sale in future state of completion (VEFA). The buyer signs a reservation contract, pays staggered funds according to the progress of construction, and then takes possession of the property upon delivery. This mechanism places the developer at the center of the process, well before the notary or loan establishment.
VEFA Delivery Clause: What the Completion Guarantee Does Not Cover
The financial completion guarantee (GFA) provides reassurance, but its scope is narrower than one might think. It comes into play if the developer can no longer finance the completion of the project. However, it does not cover late penalties or additional rents incurred by the buyer during the waiting period.
The distinction is concrete. A financially troubled developer will see the guarantor complete the building. A solvent but disorganized developer will deliver late without the GFA triggering anything. The late penalties depend solely on the delivery clause included in the VEFA contract.
Before signing, check two elements in this clause: the daily penalty amount provided in case of overruns, and the list of causes for suspending the deadline (bad weather, strikes, subcontractor failure). The developer must justify each day of suspension with documented evidence. The burden of proof lies with them, not the buyer.
Comparing new real estate projects on Immotive allows for cross-referencing several programs and assessing the contractual transparency of each developer from the research phase.

Financial Stability of the Developer: Signals to Check Before Purchase
The reliability of a developer is not measured solely by their commercial reputation. Their financial health directly conditions the successful completion of the project. An undercapitalized developer may slow down work, renegotiate with suppliers, or, in the worst case, face collective proceedings.
Several signals are accessible without accounting expertise:
- The age of the company and the number of programs already delivered, verifiable through public records and online reviews from former buyers.
- The presence of a clearly identified bank guarantor in the reservation contract, rather than a vague mention.
- Compliance with fund requests according to the legal schedule: any unusual delay may signal a cash flow problem.
A reliable developer spontaneously communicates about their guarantor and references. Opacity on these subjects is a more telling warning sign than any commercial argument.
Inspection at Delivery and One-Month Deadline: An Underutilized Legal Lever
On the day of key handover, the buyer signs a delivery report. This document lists the reservations, that is, the visible defects observed on site: a crack in a tile, a poorly positioned socket, a door that rubs. The developer must correct these points within a reasonable timeframe.
What many buyers do not know is that the one-month period after the handover remains open to report defects. According to Article 1642-1 of the Civil Code, apparent defects or non-compliance issues not recorded in the report can still be notified in writing to the developer within thirty days after taking possession.
Why Schedule a Second Inspection After a Few Days
On the day of delivery, stress and logistics reduce vigilance. Some defects only reveal themselves with use: a noisy ventilation system at night, slow water drainage, a roller shutter that jams in cold weather.
Plan a methodical visit in the week following the move-in. Note each anomaly in writing, with dated photos, and then send a registered letter to the developer before the one-month deadline expires. This letter has the same legal value as the reservations in the report.

VEFA Contract and Financing: The Steps That Truly Commit the Buyer
The VEFA purchasing process involves distinct commitment levels. The reservation contract sets the price, the description of the property, and the estimated delivery date. A deposit is paid, capped by law according to the timeline for the sale’s completion.
The authentic deed signed at the notary transforms the reservation into a firm sale. From this moment, the fund requests follow the progress of construction. Financing through a mortgage must be finalized before this signature: the release of funds follows the pace of the construction, not that of the buyer.
Coordinating the Mortgage with the VEFA Schedule
The gap between obtaining the loan and the first fund request generates interim interest. These costs, often underestimated, accumulate as long as the property is not delivered. The longer the construction takes, the higher the bill.
Negotiate with your bank for a total repayment deferral if your budget allows. Also, ensure that the loan offer explicitly includes the possibility of a delivery delay without additional bank penalties.
A well-prepared new real estate project relies less on blind trust than on careful reading of three documents: the delivery clause, the financial completion guarantee certificate, and the loan offer. These documents, cross-referenced with the developer’s references, form the foundation of a controlled investment.